Which of the following correctly describes a Direct Implementation Process?

Study for the BCS Foundation Certificate in Business Change Exam. Enhance your knowledge with flashcards and multiple-choice questions, with hints and explanations for each question. Prepare thoroughly for your exam!

The correct answer describes a Direct Implementation Process accurately as the scenario where the old system is completely retired, and the new system goes live all at once, often referred to as 'The big bang' approach. This method signifies a complete transition from one system to another without any overlap or gradual phase-in of components.

This approach is characterized by its immediacy, which can be advantageous in situations where the new system is expected to be significantly better and there’s confidence in its performance. The excitement and momentum associated with launching a new system can lead to a fresh start, allowing users to fully embrace the new system without carrying over familiarities or dependencies from the old one. However, it is important to note that this method carries risks, as it can result in significant disruption if issues arise during the transition, given that there is no fallback option to rely upon.

By understanding the definition of Direct Implementation, you can better appreciate the context of system transitions in business change practices and assess the advantages and disadvantages of different implementation strategies.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy